Case Farms
City: Winesburg
State: OH
Size of Project: 26,000 SF Process Area & 154,000 SF Freezer
Completion Date: July 2021
Project Type: Spec
Details: Refrigerated Process & Freezer Facility Expansion
Key Tasks:
(4) 4000 Amp Main Services, Distribution Equipment, Emergency Generator Quick Connects, VRT Hookups, Hygienic Unit Hookups, Pump Hookups, Boiler Hookups, Hot Water Tank Hookups, Refrigeration Compressor Hookups, Condensing Tower Hookups, Evaporator Hookups, HVAC Equipment Hookups, LED Wash down Lighting, LED Interior Lighting, LED Exterior Lighting, Wash down Rated Receptacles, Stainless Steel Conduit, High Speed Door Hookups, Dock Door Hookups, Battery Charger Hookups, Fire Alarm System, and 6,500 SF Office Electrical Finish.