GE Aviation
City: Ellisville
State: MS
Size of Project: 300,000 SF
Completion Date: July 2013
Project Type: Design Build
Details: New 10 MW Manufacturing Facility for GE Aircraft Engines
Key Tasks:
(5) 3,750 KVA-33,500 KV-480/277 Volt Transformers, (5) 4000 Amp Main Switchboards, Distribution Equipment, 6000′ of Busduct Runs, 450 KW Generator and ATS, HVAC Hookups, Extruder Hookups, Autoclave Hookups, Florescent Lighting, Metal Halide Site Lighting, Dock Commander Hookups, Fire Pump Hookup, Data/Telephone System, Fire Alarm System and Office Electrical Finish.