Skip to content

GE Aviation

City: Ellisville

State: MS

Size of Project: 300,000 SF

Completion Date: July 2013

Project Type: Design Build

Details: New 10 MW Manufacturing Facility for GE Aircraft Engines

Key Tasks:

(5) 3,750 KVA-33,500 KV-480/277 Volt Transformers, (5) 4000 Amp Main Switchboards, Distribution Equipment, 6000′ of Busduct Runs, 450 KW Generator and ATS, HVAC Hookups, Extruder Hookups, Autoclave Hookups, Florescent Lighting, Metal Halide Site Lighting, Dock Commander Hookups, Fire Pump Hookup, Data/Telephone System, Fire Alarm System and Office Electrical Finish.